Lead times: why the order date matters as much as the start date

Most project delays don't happen on the jobsite. They happen weeks earlier, when a selection wasn't made, an order wasn't placed, or something was changed after it was ordered. Here is what lead times are, which items usually take the longest, and how you can help keep your project on schedule.

What a lead time is

A lead time is the time between placing an order and the item arriving at the job. The key word is placing. The clock doesn't start when you pick a window or fall in love with a tile. It starts when the order goes in with final sizes, colors, and options confirmed, and usually a deposit paid. Anything that has to be drawn, approved, or built to order adds time before it even ships. On commercial work, it's common to add 2 to 6 weeks for submittals and approvals on top of fabrication time (Terrapin Construction Group).

Why one late item can stop everything

Construction happens in a sequence, and each stage depends on the one before it. The National Association of Home Builders breaks a typical new house into stages: site work and foundation, framing, rough-ins for HVAC, plumbing, and electrical, exterior finishes like siding, roofing, windows, and doors, and interior finishes like drywall, cabinets, countertops, fixtures, and flooring. Interior finishes take the longest, at an average of 6.4 weeks (NAHB).

Here's how one late item spreads:

The crew isn't sitting idle by choice. The next step physically can't happen until the item is there.

Items that usually take the longest

Lead times change with the manufacturer, the season, and the market, so we check current lead times with suppliers when we bid and again when we order. These are the items we watch most closely:

Commercial projects have their own long-lead items, like storefront glass, rooftop units, and electrical gear. On larger buildings that need new electrical service, medium-voltage switchgear was running 52 to 80 weeks as of July 2026 (Terrapin Construction Group). See our tenant finish-out timeline.

Selections drive the design, too

Some choices have to be made before the drawings can be finished or the walls can close, even if the item won't be installed for months:

Why changes cost more than they seem

Changing a selection after it's ordered usually means canceling, possibly paying a restocking fee or losing a deposit on custom items, and restarting the lead time from zero. If the change affects something already built, like a framed opening or a plumbing rough-in, that work gets redone too. A small change late in the job can cost weeks.

What you can do

How we plan around lead times

We flag long-lead items during the bid, build the schedule around their delivery dates, and confirm the order before demolition or framing depends on it. Deliveries are checked when they arrive, because a damaged unit found on install day restarts the clock. See how this fits into a real schedule in our kitchen remodel timeline, bathroom remodel timeline, and home addition timeline, or request an estimate and we'll walk through the order dates with you.

Related services and guides

More from the blog

Questions

Common questions

What is a lead time in construction?

A lead time is the time from placing an order to the item arriving at the job. It starts when the order is placed with final selections and any deposit, not when you choose the product, and items that need drawings or approvals take longer.

Which items have the longest lead times on a home project?

Windows and exterior doors, custom cabinets, countertops, special-order tile and stone, specialty plumbing fixtures, built-in appliances, HVAC equipment, structural beams and trusses, and electrical service upgrades are the items most likely to set the schedule.

Why can't the crew keep working while we wait for an item?

Construction is sequential. If windows aren't in, the house can't be dried in for insulation and drywall. If cabinets aren't set, countertops can't be measured. The next step physically depends on the missing item.

When do I need to make my selections?

Before the work that depends on them. Appliances are needed before cabinet drawings, valves before rough plumbing, light fixtures before drywall, and window sizes before framing. Long-lead items should be selected and ordered before the project starts.

Why does changing a selection delay the project?

A change usually means canceling the order, possibly paying a restocking fee or losing a deposit on custom items, and restarting the lead time from zero. If work was already built around the original choice, it has to be redone.

Should I start demolition before materials arrive?

On remodels, we recommend not tearing out a kitchen or bath until the long-lead materials are confirmed or delivered, so the room isn't out of service longer than necessary.