Kitchen remodel timeline, step by step
The order of work matters more than the calendar. Here is how a well-run kitchen remodel moves from first visit to final walkthrough, and where most delays come from.
The ten steps
Site visit and scope
We measure, photograph, and talk through layout, budget, and what has to stay.
Design and selections
Layout, cabinets, counters, tile, fixtures, appliances, and lighting are chosen and priced line by line.
Order long-lead items
Cabinets, countertops, and special-order appliances are ordered before demolition.
Permit
If the scope moves walls, plumbing, gas, or electrical, we submit the permit and wait for approval.
Protection and demolition
Dust walls and floor protection go up, then the old kitchen comes out.
Rough-in and inspection
Framing changes, plumbing, electrical, and ventilation are roughed in and inspected before walls close.
Drywall and prep
Walls and ceilings are closed, patched, and primed; flooring goes down if it runs under cabinets.
Cabinets, then countertops
Cabinets are set and leveled; countertops are templated from the installed cabinets, then fabricated and installed.
Backsplash, fixtures, and appliances
Tile, sinks, faucets, lighting, and appliances go in and are connected.
Final inspection and punch list
Final inspections, touch-up, cleaning, and walkthrough.
What sets the length
Layout changes add time: moving a sink, range, or wall means more rough-in work and usually a permit. Lead times on cabinets and countertops are often the longest wait in the whole job, which is why we order them before demolition. Older homes can hide old wiring, cast-iron drains, or soft subfloor; we open walls early so surprises show up before the schedule depends on them.
Keep it on schedule
Finalize selections before demolition, approve the itemized proposal with every line spelled out, and keep one point of contact for decisions. For an example of built-to-fit cabinetry, see our custom cabinets and vanities project. Remodeling a bath as well? See our bathroom remodel timeline. If your kitchen is part of a bigger renovation, see our full home remodeling page or our El Viejo Camino barn remodel.
Questions
Common questions
How long does a kitchen remodel take?
It depends mostly on scope and lead times. A layout change that moves plumbing, gas, or walls takes longer than a same-footprint update, and cabinets and countertops are often the longest wait. We give you a written schedule before demolition starts.
Do I need a permit for a kitchen remodel?
If you move walls, add circuits, relocate plumbing or gas, or change ventilation, almost always yes. Swapping cabinets and counters in the same layout often does not. We confirm with your city before pricing.
Why order cabinets before demolition?
Cabinets and countertops usually have the longest lead times. Ordering them before the kitchen is torn out keeps you from living without a kitchen while you wait on materials.
Can I live at home during a kitchen remodel?
Usually, yes. We set up dust protection and a temporary kitchen area, and keep the rest of the house usable.
What causes kitchen remodel delays?
Late selections, material backorders, hidden conditions behind walls such as old wiring or rotted subfloor, and failed inspections. Finalizing selections early and opening walls early cuts most of that risk.