A bathroom packs plumbing, electrical, ventilation, waterproofing, and tile into a small room, so the order of work decides how long it takes. Here is how a well-run bath remodel moves from first visit to final walkthrough.

The eleven steps

  1. Site visit and scope

    We measure, check the plumbing and framing we can see, and talk through layout, storage, and what has to stay.

  2. Design and selections

    Layout, vanity, tile, shower or tub, fixtures, mirrors, lighting, and ventilation are chosen and priced line by line.

  3. Order long-lead items

    Custom or special-order vanities, tile, and fixtures are ordered before demolition.

  4. Permit

    If the scope moves plumbing, walls, or electrical, or adds an exhaust fan, we submit the permit and wait for approval.

  5. Protection and demolition

    Floors and the path through the house are protected, then the old bath comes out down to the studs and subfloor where needed.

  6. Framing and subfloor repair

    Rotted subfloor and framing from old leaks are replaced, and niches, blocking for grab bars, and the shower curb are framed.

  7. Rough-in and inspection

    Drains, supply lines, valves, wiring, lighting, and the exhaust fan are roughed in and inspected before walls close.

  8. Waterproofing and tile backer

    Backer board and a waterproof membrane go on the shower walls and pan, and the shower is checked for leaks before tile.

  9. Tile

    Floor and wall tile are set and grouted, with the shower floor sloped to the drain.

  10. Vanity, fixtures, and glass

    The vanity and top, toilet, faucets, trim, mirrors, and lighting go in; frameless glass is templated from the finished tile and installed.

  11. Final inspection and punch list

    Final inspections, caulk and touch-up, cleaning, and walkthrough.

What sets the length

Moving fixtures adds time: relocating a shower, toilet, or vanity means new drain and supply lines, often a permit, and more inspections. Lead times on custom vanities, special-order tile, and shower glass are usually the longest waits, so we order them before demolition. Water damage is the most common surprise in older bathrooms; slow leaks around tubs, toilets, and showers rot subfloor and framing out of sight, and we open the floor early so repairs happen before tile is scheduled.

Don't rush the waterproofing

Tile and grout aren't waterproof on their own. What keeps water out of the walls and floor is the membrane and shower pan behind the tile, so we give that step its own time and test it before tile goes on. It's the one step you never see in the finished room and the one that matters most.

Keep it on schedule

Finalize selections before demolition, approve the itemized proposal with every line spelled out, and keep one point of contact for decisions. For examples of built-to-fit vanities and linen towers, see our custom cabinets and vanities project. Remodeling the kitchen too? Read our kitchen remodel timeline, or see our full home remodeling page and the Wesson whole-home remodel.

Questions

Common questions

How long does a bathroom remodel take?

It depends mostly on scope and lead times. Replacing fixtures and tile in the same layout moves faster than a full gut that relocates the shower, toilet, or vanity, and custom vanities, special-order tile, and shower glass are often the longest waits. We give you a written schedule before demolition starts.

Do I need a permit to remodel a bathroom?

If you move plumbing, add or change circuits, move walls, or add an exhaust fan, usually yes. Swapping a vanity, toilet, or faucet in the same spot often does not. Rules vary by city, so we confirm with yours before pricing.

Why does the shower glass go in last?

Frameless glass is measured from the finished tile, so the installer can't template it until tile and grout are done. Expect a short wait between tile and glass, which is why we order the glass as soon as tile is set.

Can I convert a tub to a walk-in shower?

Usually, yes. The drain has to move to the shower location and the floor needs proper slope to the drain, plus new waterproofing behind and under the tile. We check the framing and drain path on the site visit.

What causes bathroom remodel delays?

Late selections, backordered tile or fixtures, rotted subfloor or framing found after demolition, and failed inspections. Finalizing selections early and opening the floor and walls early cuts most of that risk.