Tenant finish-out timeline, step by step
Most of a commercial finish-out schedule is decided before anyone swings a hammer: the lease, the design, accessibility registration, the permit, and equipment lead times. Here is the order a well-run office, retail, medical, or restaurant build-out follows in Austin, from the first walk of the space to the certificate of occupancy.
The twelve steps
Walk the space before you sign
We walk the suite with you, note the shell condition, existing walls, ceilings, restrooms, HVAC, electrical service, and sprinklers, and flag what is likely to need upgrading.
Read the lease and work letter
The work letter decides who builds what and how much the tenant improvement allowance covers. We price the scope against it so you know where the allowance runs out.
Design and engineering
Your architect and MEP engineers draw the floor plan, reflected ceiling, power, plumbing, and mechanical plans. We price as the design develops so the budget stays in view.
Itemized proposal and landlord approval
One itemized proposal with a lump-sum total, then landlord review of the plans, contractor insurance, and building rules.
TDLR registration
Projects of $50,000 or more are registered with TDLR and the plans go to a Registered Accessibility Specialist for review.
Commercial permit
The permit set is submitted to the city, review comments are answered, and the building and trade permits are issued.
Order long-lead items
Rooftop units, electrical panels and gear, storefront and glass, doors and hardware, and kitchen equipment are ordered right away, since they often set the finish date.
Demolition and layout
Old finishes, walls, and ceilings come out, and new walls, plumbing, and power locations are laid out on the slab.
Underground plumbing and framing
Floor trenching for new restrooms or sinks, then metal stud framing, demising walls, door frames, and blocking. Underground and framing are inspected.
MEP and fire rough-ins
Electrical, plumbing, HVAC ductwork, data, and fire sprinkler and alarm changes are roughed in and inspected above the ceiling and in the walls.
Drywall, ceilings, and finishes
Insulation, drywall, ceiling grid and tile, paint, flooring, millwork, restroom fixtures, lighting, and trim.
Final inspections and certificate of occupancy
Building, trade, fire, and health inspections where they apply, the TDLR accessibility inspection, a punch list, and the certificate of occupancy so you can open.
What sets the length
Paperwork usually takes longer than the build. Design, landlord approval, TDLR registration, and commercial plan review run in sequence, so a decision made late in design pushes everything behind it. Long-lead equipment sets the finish date. Rooftop HVAC units, switchgear, storefront glass, and restaurant hoods can take longer to arrive than the framing and drywall take to build, so we order them as soon as the design is approved. Shell condition matters. A cold dark shell needs utilities, HVAC, and restrooms from scratch, while second-generation space may reuse some of what is there but often needs demolition and code upgrades. See TI allowances and shell types and what drives finish-out cost.
Plan backward from your rent start date
Most leases set a rent commencement date, often tied to a fixed number of days after the space is delivered or to the day you open, whichever comes first. If the build-out runs past that date, you can end up paying rent on a space you can't use yet. That's why we build the schedule backward from the rent start date, not forward from the day the lease is signed.
- Count the city review time. Austin Development Services lists 10 business days for a commercial remodel up to 25,000 square feet and 20 business days for remodels over 25,000 square feet. Simple interior finish-outs under 10,000 square feet can use the Small Project application, reviewed in about 5 business days, and qualifying finish-outs of 5,000 square feet or less can use Quick Turnaround review in one business day (Austin Commercial Plan Review).
- Add the review rounds. Those times are per review. If the city sends comments, the update has to include written responses and the full revised plan set, and the review repeats. Starting with the second update, each update is charged a fee, so a clean first submittal saves time and money.
- Add the other approvals. Landlord plan approval, TDLR registration and RAS review for projects of $50,000 or more, and, for food businesses, Austin Public Health plan review and Austin Water's grease interceptor approval all have to fit in before or alongside the permit.
- Order long-lead items as soon as the design is set. Rooftop units, electrical gear, storefront glass, and kitchen hoods often take longer than the construction itself.
- Leave room at the end. Final inspections, the accessibility inspection, punch list, and the certificate of occupancy come last, and furniture, signage, and IT move-in follow them.
Before you sign, ask how the lease handles delays. Some leases push rent start back when the landlord's delivery work or approvals run late, and some don't. We walk the space and give you a realistic build schedule you can use while you negotiate.
Build-out while the landlord's rules apply
Commercial buildings have their own rules: work hours, freight elevator and loading dock access, noise limits near open tenants, and insurance certificates. We plan around them up front so the schedule doesn't stall on access.
See a commercial build
Our Wahoo's Fish Tacos South Shore project took a restaurant and bar from site work through finish-out. For your type of space, see office buildouts, restaurant buildouts, retail buildouts, or our main commercial tenant finish-out page. On the city side, read our Austin zoning guide and permit expediting guide. Examples shown are our own projects; every schedule depends on the space, the design, and permit review.
Questions
Common questions
How long does Austin take to review a tenant finish-out permit?
Austin Development Services lists 10 business days per review for a commercial remodel up to 25,000 square feet and 20 business days above that. Simple finish-outs under 10,000 square feet can use the Small Project application at about 5 business days, and qualifying finish-outs of 5,000 square feet or less can use Quick Turnaround review in one business day. Comment rounds add time.
How do I keep a build-out from running past my rent start date?
Plan the schedule backward from the rent commencement date: city review and comment rounds, landlord approval, TDLR review if the project is $50,000 or more, long-lead equipment, and final inspections and the certificate of occupancy. Then negotiate the lease with that real schedule in hand, including what happens if approvals run late.
Does a tenant finish-out in Austin need a permit?
Almost always. Building out or remodeling a commercial suite needs a commercial building permit plus trade permits for electrical, plumbing, and mechanical work, and the City of Austin issues a certificate of occupancy when a space is remodeled or renovated. We prepare the permit set with your architect or engineer and handle the inspections.
What is TDLR registration and when is it required?
Under the Texas Architectural Barriers Act, commercial projects with a construction cost of $50,000 or more must be registered with the Texas Department of Licensing and Regulation, and the plans are reviewed and the finished space inspected for accessibility by a Registered Accessibility Specialist. Registration happens before the city permit submittal, so it belongs at the front of the schedule.
What usually delays a finish-out?
Late design decisions, permit review comments, long-lead equipment like rooftop HVAC units, electrical gear, storefront glass, and restaurant hoods, and landlord approvals. Ordering long-lead items as soon as the design is approved is the biggest single way to protect an opening date.
Can work start before the permit is issued?
Only limited work, such as demolition when it is separately permitted or allowed by the landlord and city. New construction, rough-ins, and anything that will be inspected waits for the permit.
Do you work with the landlord's work letter?
Yes. We read the work letter, mark every line as landlord work, tenant work, or allowance-eligible, and coordinate with the property manager on access, insurance, and building rules. Call or text 737-285-2969 to schedule a walk of the space.