Certificates of occupancy in Austin: CO, TCO, and change of use
A business can't open in Austin until the space has a certificate of occupancy for the way it will be used. Here is when a finish-out needs a new one, how change of use works, when a temporary CO lets you stock the space early, and the mistakes that delay opening day.
When a CO is required
Use, occupancy, or a change of either. Austin's Land Development Code says a person may not use, occupy, or change the existing use or occupancy of a structure unless the building official has issued a certificate of occupancy for it (LDC §25-1-361). The city describes a CO as confirming that a structure is habitable for its legal use and property type and meets housing and building codes (Austin DSD).
What the building official checks. A CO is issued when the development has passed required inspections, the owner has met fiscal security requirements, and the work was completed according to the released site plan and construction plans (LDC §25-1-363). For new construction or significant renovations, the city provides the CO after a successful final inspection; if it doesn't arrive, you email DSD to request it (Austin DSD).
The last legal CO is the starting point. You can request a copy by emailing [email protected] with the address and unit number; the city asks you to allow 1 to 5 business days for up to six COs (Austin DSD). We ask for it before a lease is signed, because the use it lists decides whether your project is a change of use.
The six steps
Pull the current CO before you sign
Request the last legal certificate of occupancy for the suite from the city. It shows the use the space is approved for today, which tells you whether your business is a change of use.
Confirm zoning and the site plan
The proposed use has to be allowed by the zoning, and the permit application references the approved site plan case number or a site plan exemption.
Submit the commercial permit
A finish-out is submitted as a commercial remodel or tenant finish-out; a use change with no construction is a change-of-use submittal. Both list the current and proposed use. Small interior finish-outs may qualify for the city's Quick Turnaround review.
Build and pass trade inspections
Electrical, mechanical, and plumbing inspections follow the work, along with fire, health, or environmental inspections when the use calls for them.
Decide whether you need a TCO
If the owner needs to stock or furnish the space before every final passes, a TCO for stocking or occupancy is requested with its own inspections, and the building TCO inspection is scheduled last.
Pass the building final and receive the CO
The building official issues the CO after required inspections pass and the work matches the released plans. The CO, or the TCO until then, is posted near the main entrance.
Change of use
When a space changes from one use to another, the commercial application lists the current use from the last legal CO and the proposed use as defined in the Land Development Code, with the work described as "change of use from (current use) to (proposed use)" (Austin change-of-use submittal requirements). Even with no remodel, the city asks for a scaled floor plan showing each room's use, restrooms, exits, the complete exiting system, the occupancy of adjoining suites, and the accessible route from parking to the front door, plus the approved site plan number or exemption. Plan reviews expire one year from the date of application. If construction is part of the job, it follows the remodel and tenant finish-out submittal instead, and the city's Commercial Plan Review division reviews changes of use and certificates of occupancy along with remodels (Austin Commercial Plan Review).
Temporary certificates of occupancy
Stocking or occupying early. A TCO may allow a property to be occupied, stocked, or furnished before the final CO (Austin DSD), and the building official may issue one if the use isn't a hazard to life, health, or public safety (LDC §25-1-364).
Don't move in first. Austin's commercial TCO procedures say a structure can't be occupied or stocked with materials, furniture, or merchandise until a TCO or CO is issued. If it is, the TCO or CO is denied, an automatic nonrefundable fee applies, and temporary utility approval can be withdrawn (Austin commercial TCO procedures). The trade, fire, health, and environmental TCO inspections come first, and the building TCO inspection is the last one scheduled. The TCO is posted next to the main entrance until the permanent CO replaces it.
90 days. The city's TCO flowchart says a TCO for occupancy expires after 90 days and must be renewed with a fee and a new inspection, while a TCO for stocking is allowed for 90 days with no renewal (Austin TCO flowchart).
Where opening dates slip
The most common delays we plan around are a proposed use the zoning doesn't allow, a site plan question that surfaces late, furniture or inventory delivered before a TCO, and a final inspection that can't be scheduled because one trade or the fire final is still open. Commercial finish-outs of $50,000 or more also go through the state TDLR accessibility review. See how it all lines up in our tenant finish-out timeline, check the zoning basics in our Austin zoning guide, or see our commercial finish-out work. Outside Austin, the rules differ; in Bee Cave, for example, the fire inspection goes through Lake Travis Fire Rescue (Bee Cave guide). This page is a general overview, not legal advice; the City of Austin confirms what applies to a specific address.
Questions
Common questions
Do I need a new certificate of occupancy for a new tenant in Austin?
You need a certificate of occupancy that matches how the space will be used. Austin's Land Development Code says no one may use, occupy, or change the existing use or occupancy of a structure without one. If your use differs from the last legal CO, or the space is remodeled under a permit, a new CO comes at the end of that process.
How do I get a copy of the current certificate of occupancy?
Email the City of Austin at [email protected] with the address and unit number. The city asks you to allow 1 to 5 business days for up to six COs; seven or more go through a Public Information Request.
What is a change of use?
A change of use is when a space goes from one legal use to another, for example from retail to restaurant or from office to medical. The permit application lists the current use from the last legal CO and the proposed use as defined in the Land Development Code. If there's no construction, a change-of-use submittal still needs a floor plan showing restrooms, exits, and the accessible route from parking.
Can we move furniture or stock in before the final CO?
Not without a temporary certificate of occupancy (TCO). Austin's commercial TCO procedures say a structure can't be occupied or stocked with materials, furniture, or merchandise until a TCO or CO is issued, and doing so gets the TCO or CO denied with an automatic nonrefundable fee.
How long does a TCO last in Austin?
The city's TCO flowchart says a TCO for occupancy expires after 90 days and has to be renewed with a fee and a new inspection, and a TCO for stocking is allowed for 90 days with no renewal. Any restrictions written on the TCO apply until they are cleared.
Does the contractor get the certificate of occupancy?
On a permitted finish-out, the CO follows the building final inspection, so we schedule and pass the trade, fire, and building finals that lead to it. If the CO doesn't arrive after a final, the city says to email DSD to request it. Call or text 737-285-2969 to walk your space.