TDLR accessibility review for tenant finish-outs

In Texas, most commercial finish-outs of $50,000 or more go through a state accessibility process run by the Texas Department of Licensing and Regulation (TDLR), on top of the city permit. Here is when it applies, how it works, and the deadlines owners and tenants miss most often.

When it applies

The $50,000 line. Under the Texas Architectural Barriers Act, projects with a total estimated cost of $50,000 or more must be registered with TDLR, and a full set of construction documents goes to a Registered Accessibility Specialist (RAS) for review (TDLR, Architectural Barriers at a Glance). The Act covers publicly funded buildings, commercial facilities, and public accommodations such as offices, retail, restaurants, and medical suites.

Under $50,000 still has to comply. TDLR says smaller projects don't have to be registered or reviewed, but they are still required to comply with the Texas Accessibility Standards (TAS) (TDLR FAQ). A local building official may require registration even below $50,000, and owners can register a smaller project voluntarily with a special registration (TDLR).

What counts toward the cost. Fees are based on the estimated construction cost, not including site acquisition, furnishings, or equipment that isn't part of the building's mechanical systems (TDLR fee schedule).

The seven steps

  1. Confirm the project is subject and the estimated cost

    Commercial facilities and public accommodations with an estimated construction cost of $50,000 or more must be registered. The estimate excludes land, furnishings, and equipment that isn't part of the building's mechanical systems.

  2. Choose a Registered Accessibility Specialist

    The owner hires a RAS, a TDLR-licensed reviewer and inspector. The RAS's license number is required to register the project.

  3. Register the project in TABS

    Registration is done online in the Texas Architectural Barriers online System (TABS), not by mail, with the filing fee paid by credit card. TDLR issues a project number.

  4. RAS plan review

    A full set of construction documents goes to the RAS, who reviews it against the Texas Accessibility Standards and reports findings to the owner and TDLR. Comments are resolved in the drawings before construction.

  5. City permit and construction

    The city permit runs alongside. During the build we watch the details that fail most often: door clearances and hardware, restroom layouts and grab bars, counter and sink heights, routes, and signage.

  6. Request the RAS inspection

    TDLR rules call for requesting an inspection within 30 days after construction is complete. The RAS inspects the finished space.

  7. Correct any deficiencies

    If the inspection report lists corrections, the owner responds to the RAS on TDLR's form within 30 days of the report and completes the work. The inspection itself must happen no later than the first anniversary of completion.

Fees and deadlines

Registration. Registration is online through TABS; TDLR's help sheet lists a $175 registration fee, or $300 if registered late, and requires the license number of your chosen RAS (TDLR registration help sheet). Registration can't be done by mail (TDLR form EAB-205N). The RAS charges separately for plan review and inspection.

Inspection. The owner is responsible for having the facility inspected by a RAS no later than one year after construction is complete. TDLR's enforcement plan lists missing that deadline, and failing to request an inspection within 30 days of completion, as violations (TDLR penalties and sanctions). Corrections from an inspection report are answered on TDLR's form within 30 days of the report (TDLR training on the rules).

Where finish-outs get caught

Second-generation spaces often have older restrooms, doors, and counters that don't meet the 2012 TAS (TDLR). When a suite is altered, those elements and the route to them can become part of the scope. We look for them on the first walk of the space, before the lease is signed, so the budget includes them. Read more in what drives finish-out cost and the TI allowance guide.

How it fits the schedule

Registration and RAS plan review run alongside design and the city permit, and the RAS inspection comes at the end with the certificate of occupancy. See the full order in our tenant finish-out timeline, or see current work at our Hill Country Galleria finish-out. This page is a general overview, not legal advice; your architect and RAS confirm what applies to a specific project.

Questions

Common questions

When does a tenant finish-out need TDLR registration?

When the building is subject to the Texas Architectural Barriers Act, which covers commercial facilities and public accommodations, and the estimated construction cost is $50,000 or more. Those projects are registered with TDLR, the plans are reviewed by a Registered Accessibility Specialist (RAS), and the finished space is inspected.

What if the project costs less than $50,000?

TDLR says registration and review are not required under $50,000, but the work must still comply with the Texas Accessibility Standards. A city building official can also require registration on a smaller project, and an owner can choose to register voluntarily with TDLR's special project registration.

How much is the TDLR registration fee?

TDLR's registration help sheet lists a $175 registration fee, or $300 if registered late, paid by credit card when the project is registered online in TABS. Plan review and inspection fees are paid separately to the RAS.

Who is responsible for the accessibility inspection?

The building or facility owner. Under the Act the owner must have the project inspected by a RAS no later than one year after construction is complete, and TDLR treats a missed inspection as a Class A violation. In a lease, the work letter should say who arranges and pays for it.

Does TDLR registration replace the city permit?

No. TDLR covers state accessibility compliance; the city or other local jurisdiction still issues the building permit and certificate of occupancy. Some cities ask for proof of TDLR submission with the commercial permit application.

Do you handle TDLR registration on finish-outs?

Yes. We coordinate registration, the RAS plan review, and the final RAS inspection alongside the city permit, and we build to the reviewed plans. Call or text 737-285-2969 to walk your space.