Design around the tree first
Start with a tree survey and draw every critical root zone on the site plan before anything else. In Austin, at least 50 percent of the CRZ has to stay at natural grade, the half CRZ allows no more than 4 inches of cut or fill, and the quarter CRZ allows none (Environmental Criteria Manual, Section 3). Redesigning after a plan review rejection costs far more than designing around the tree the first time. For the size and species thresholds, see our guide to Austin heritage tree rules.
Design moves that keep the tree
- Shift, rotate, or reshape the footprint. An L-shaped or offset plan can wrap around a root zone that a simple rectangle would hit.
- Build up, not out. A second story adds space without adding footprint inside the CRZ.
- Span over the roots. The City lists elevated foundations that span or cantilever over the CRZ as an alternative. They are anchored outside the half CRZ or on piers dug with low-impact excavation (City of Austin Tree Smart guide). On wooded lots, we often use pier-and-beam sections or bridged grade beams near the tree instead of a full slab.
- Reuse old impacts. If an old driveway or utility line already runs through a CRZ, new work can follow the same footprint, as long as it is no wider and no deeper (Tree Smart guide).
- Route utilities on purpose. Water, sewer, gas, and electric lines are trenches. Plan the routes outside the half CRZ, or use air tools and other low-impact excavation where they have to pass near roots.
- Ask about setback relief. For heritage trees under 30 inches, an administrative removal variance requires showing that you sought other variances first, such as setback relief (Austin heritage tree ordinance). Moving the house a few feet is often the easier approval anyway.
Job-site rules once construction starts
Tree protection goes up before any clearing, grubbing, or grading, and it stays up until the job is done (City of Austin tree preservation plan notes). The main requirements:
- Fencing. Chain-link mesh at least 5 feet tall on steel T-posts no more than 10 feet apart, continuous around the CRZ. Plastic fencing isn't allowed, and the fenced area can't be used to store tools or materials (ECM Section 3).
- Mulch. Any part of the CRZ that isn't fenced and isn't approved for impacts gets 8 to 12 inches of natural wood mulch, never piled against the trunk, and removed at the end. Disturbed soil inside the fence gets 3 inches, and mulch inside the half CRZ is topped with decking (ECM Section 3; Tree Smart guide).
- Trunk wrap. Required when the fence sits within 5 feet of the trunk or low limbs could be hit by equipment (Tree Smart guide).
- Keep the root zone clean. City plan notes bar concrete and paint washout, portable toilets, and dumpsters anywhere in the full CRZ. Where equipment has to roll over mulch, filter fabric goes underneath and mats or plywood go on top (tree preservation plan notes).
- No over-digging. The same notes prohibit over-excavating the foundation or compacting soil inside a half CRZ, and allow only pointed rebar for form and batter board stakes there.
- Prune carefully. No more than 25 percent of the living crown can be removed (Tree Smart guide). Clearance pruning for the roof and scaffolding has to fit inside that limit.
What happens if a tree gets hurt
Austin defines removal as anything that causes, or can reasonably be expected to cause, a tree to die. That includes damaging the root system and excessive pruning (Tree Smart guide). So a trench through the half CRZ can be treated like cutting the tree down. For a heritage tree, mitigation is 300 percent of the diameter, so a damaged 24-inch oak can mean 72 inches of replacement trees or $14,400 at the City's $200-per-inch rate. Environmental inspectors can also issue red tags and stop-work orders (City of Austin). The cheapest tree protection is a fence that never moves.
The rules are moving
Austin has proposed amendments to the tree section of its Environmental Criteria Manual covering mitigation credits and protection for smaller trees (proposed rule R161-26.04). It is also running a Small Tree Fee Credit pilot that refunds some development fees when builders save trees under 19 inches on new single-family homes, with applications accepted through May 28, 2027 (City of Austin). And a federal lawsuit filed in 2026 challenges how the City calculates mitigation (Austin American-Statesman). Confirm current rules with the City Arborist before you lock a layout.
How we handle it
On wooded lots, we put the CRZs on the plan before the floor plan is drawn, price the foundation and utility routes around them, and set the fence before the first machine shows up. Near roots, we plan for hand digging or air tools, and we recommend a certified arborist whenever a tree's health is in question. Buying a lot first? Read what to check before you close, then call or text 737-285-2969 to walk the site.